February Progress at a Glance




February Summary
​Construction continues throughout the job site. Slab on grade placement was completed in Area C. The layout and installation of MEP hangers has occurred in the areas that have a slab placed. Completed underground work for electrical and plumbing. Continue to install roof blocking and roofing materials. The installation of secondaries and the National Grid primary service conduits for the site. And mobilized to the begin the installation of the spray on fireproofing.
1 Month Look Ahead
-
Slab on deck layout and sleeves for all penetrations
-
3rd of 5 total deck placement
-
Kitchen and Mechanical room layout and installation of plumbing and electrical
-
Prep remaining slab on grade placement
-
Continue with roofing and fireproofing throughout the building
Upcoming SBC/PBC Meeting
April 14, 2026: SBC/PBC Meeting
Meeting Link:
https://us06web.zoom.us/j/89476547116?pwd=Zd3Zaa3kt9MOaq5jZmCmfziaytNY8V.1​
​​​Meeting ID: ​
​894 7654 7116
Passcode: ​
​ 556788
One tap:
+13092053325,,89476547116#,,,,*556788# US