top of page
March Progress at a Glance




March Summary
-
Prepped and placed slab on deck at Building C
-
Completed all underground utilities
-
Prepped subgrade for all slab on grade placements
-
Continue installing roof systems
-
Bldg C exterior framing and interior framing of corridors and classrooms
-
Mobilize and begin installation of spray fireproofing
1 Month Look Ahead
-
Continue slab on grade placements
-
Starting overhead mechanical, electrical, and fire protection rough
-
Starting B, A1 and A2 exterior framing and interior framing of corridors and classrooms
-
Continuing roof installation
-
Prep for generator and transformer pads
Upcoming SBC/PBC Meeting
May 12, 2026: SBC/PBC Meeting
Meeting Link:
https://us06web.zoom.us/j/88628465813?pwd=dxu4tQEZR1ao1kXuW4L91zAFbq1BlL.1​
​​​Meeting ID: ​
886 2846 5813
Passcode: ​
338208
One tap:
+13052241968,,88628465813#,,,,*338208# US
Quick Insights
bottom of page
