top of page
April Progress at a Glance




April Summary
-
Prepped and placed slab on grade in B and A1 building
-
Masonry completed for elevator shaft
-
Finished fire protection rough in C building floor
-
C building finished exterior framing
-
Continuing fireproofing and roofing throughout building
-
Install B stair
1 Month Look Ahead
-
Continue overhead rough in building A & B
-
Install two of three stairs in buildings A1 and A2
-
Anticipating slab on grade placements completed in remaining sections
-
CMU installation in gymnasium
-
Begin brick installation on C building
Upcoming SBC/PBC Meeting
June 9, 2026: SBC/PBC Meeting
Meeting Link:
​https://us06web.zoom.us/j/89209157462?pwd=SUIfgbrNKUobhyNLvauxnU6naxOiap.1​
​​​Meeting ID: ​
​892 0915 7462
Passcode: ​
​881550
One tap:
+16468769923,,89209157462#,,,,*881550# US (New York)
​
Quick Insights
bottom of page
