January Progress at a Glance

DJI_20260123092543_0005_D.JPG
logo_2026-01-28_10-27-24.jpeg

January Summary

Construction continues throughout the job site. The steel erection detailing has been substantially completed. Slab on deck has been placed in Building C. Roofing work started in Building C. MEP and framing layout and installation has begun in Building C. The underslab utility work has continued through the building.

1 Month Look Ahead

  • Slab on grade placement for Building C

  • Continuing the roofing installation

  • Underground electrical and plumbing continues

  • Continue installing the roof blocking

  • Mobilizing and beginning installation of fireproofing

  • Ongoing dampproofing

Upcoming SBC/PBC Meeting

Time-Lapse Video 

June 2025 - January 2026

For additional construction updates , refer to the construction page

Meeting Link: 

https://us06web.zoom.us/j/86963684354?pwd=bq0ffqy0OBaDQa6eYbWUFAiLl7HyE0.1

​​​Meeting ID: ​869 6368 4354

Passcode: ​782729

One tap: +16468769923,,86963684354#,,,,*782729# US (New York)

March 10, 2026: SBC/PBC Meeting

Quick Insights

MSBA-BRANCO.png
Selo da cidade de Clinton.png
Logotipo DW - Color_Combined Logo - square.png
LPAA.png
Fontaine_edited.jpg
  • Facebook
  • Twitter
  • YouTube

© 2023 Clinton Public Schools

O objetivo do site é fornecer informações relacionadas ao projeto de construção da Clinton Middle School.

bottom of page